STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the New South Wales Region on 31/10/2019
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1430 hrs to 1830 hrs 31/10/2019.
The forecast capacity reserve requirement is 1432 MW.
The minimum capacity reserve available is 1137 MW.
Danushka Sooriyadasa
AEMO Operation
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the New South Wales Region 30/10/2019
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 70773 is cancelled at 1400 hrs 29/10/2019.
Danushka Sooriyadasa
AEMO Operations
RESERVE NOTICE MT PASA PUBLICATION 29 October 2019
The delay in publication of results is due to a systems issue which has since been resolved.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 70774 has been updated at 1330 hrs to the following:
From 1100 hrs 30/10/2019 to 1230 hrs 30/10/2019.
The contingency forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 1137 MW.
From 1600 hrs 30/10/2019 to 1700 hrs 30/10/2019.
The contingency forecast capacity reserve requirement is 1522 MW.
The minimum capacity reserve available is 1421 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/10/2019
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 70775 is cancelled at 1330 hrs 29/10/2019.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/10/2019
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1430 hrs 30/10/2019 to 1600 hrs 30/10/2019.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 680 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/10/2019
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1330 hrs 30/10/2019 to 1600 hrs 30/08/2019.
The forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 947 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the New South Wales Region on 30/10/2019
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1530 hrs to 1600 hrs 30/10/2019.
The forecast capacity reserve requirement is 973 MW.
The minimum capacity reserve available is 968 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Danushka Sooriyadasa
AEMO Operations
RESERVE NOTICE MT PASA PUBLICATION 29 October 2019
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 70647 published on 22 October 2019.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/-/media/Files/Stakeholder_Consultation/Consultations/Electricity_Consultations/2018/RSIG-Final/Reliability-Standard-Implementation-Guidelines-June-2018.pdf
Forecasting
AEMO