74558MARKET INTERVENTION29/02/2020 03:50

Update - Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 74554

The synchronous generating units expected to be synchronised in SA from 0730 hrs 01/03/20 to the end of the Pre-dispatch period published at 1500 hrs 29/02/20 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1700 hrs 29/02/20, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
74557RECLASSIFY CONTINGENCY29/02/2020 03:48

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 29/02/2020 15:48 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74556RECLASSIFY CONTINGENCY29/02/2020 03:19

Reclassification of a Non-Credible Contingency Event: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV line and Strathmore-Clare South 7208 132kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville Nth-Clare Sth Tee King Creek 7128 132kV and Strathmore-Clare South 7208 132kV

Duration: 29/02/2020 15:19 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74555RECLASSIFY CONTINGENCY29/02/2020 03:17

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 29/02/2020 15:17 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74554MARKET INTERVENTION29/02/2020 03:04

Update - Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 74551

The synchronous generating units expected to be synchronised in SA from 0730 hrs 01/03/20 to the end of the Pre-dispatch period published at 1500 hrs 29/02/20 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
74553RECLASSIFY CONTINGENCY29/02/2020 02:54

Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Cancellation time: 29/02/2020 14:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74552

Auto-generated on behalf of Manager NEM Real Time Operations
74552RECLASSIFY CONTINGENCY29/02/2020 12:50

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 29/02/2020 12:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74551MARKET INTERVENTION29/02/2020 04:23

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The combination of synchronous generating units currently expected to be synchronised in SA from 1700 hrs 01/03/2020 will not provide sufficient system strength in SA to maintain the power system in a secure operating state.

In the absence of sufficient market response AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised from 1700 hrs 01/03/2020 to maintain power system security in SA. Refer to current Transfer Limit Advice for SA system strength on AEMO's website.

If necessary, AEMO will estimate and publish the latest time at which AEMO would need to intervene after the 1230 hrs predispatch run on the 29/02/2020

Manager NEM Real Time Operations
74550INTER-REGIONAL TRANSFER29/02/2020 02:12

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No. 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0210 hrs 29/02/2020

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details

Manager NEM Real Time Operations