70808GENERAL NOTICE30/10/2019 10:28:12 PM

Network Augmentation Commissioned - Vic Region - 30/10/2019

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the Vic region as follows:

Haunted Gully Terminal Station has been cut into the existing Moorabool-Tarrone No. 1 500 kV Transmission line to form the following circuits:

Moorabool-Haunted Gully No. 1 500 kV Transmission line
Haunted Gully-Tarrone No. 1 500 kV Transmission line

At Haunted Gully Terminal Station, the following plant has been commissioned:
No. 1 500 kV bus
No. 2 500 kV bus
1-2 500 kV bus tie

Manager NEM Real Time Operations
70807PRICES SUBJECT TO REVIEW30/10/2019 10:25:16 PM

[EventId:201910302230_review] Prices for interval 30-Oct-2019 22:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2225 hrs on 30 October 2019

PRICES ARE SUBJECT TO REVIEW for dispatch interval 30-Oct-2019 22:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
70806PRICES SUBJECT TO REVIEW30/10/2019 10:20:10 PM

[EventId:201910302225_review] Prices for interval 30-Oct-2019 22:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2220 hrs on 30 October 2019

PRICES ARE SUBJECT TO REVIEW for dispatch interval 30-Oct-2019 22:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
70805PRICES SUBJECT TO REVIEW30/10/2019 10:15:15 PM

[EventId:201910302220_review] Prices for interval 30-Oct-2019 22:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2215 hrs on 30 October 2019

PRICES ARE SUBJECT TO REVIEW for dispatch interval 30-Oct-2019 22:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
70804RESERVE NOTICE30/10/2019 10:13:02 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 31/10/2019

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 70801 has been updated at 2200 hrs to the following:

From 1430 hrs 31/10/2019 to 1830 hrs 31/10/2019.
The forecast capacity reserve requirement is 1501 MW.
The minimum capacity reserve available is 1195 MW.

Manager NEM Real Time Operations
70803PRICES SUBJECT TO REVIEW30/10/2019 10:10:12 PM

[EventId:201910302215_review] Prices for interval 30-Oct-2019 22:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2210 hrs on 30 October 2019

PRICES ARE SUBJECT TO REVIEW for dispatch interval 30-Oct-2019 22:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
70802PRICES SUBJECT TO REVIEW30/10/2019 10:05:15 PM

[EventId:201910302210_review] Prices for interval 30-Oct-2019 22:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2205 hrs on 30 October 2019

PRICES ARE SUBJECT TO REVIEW for dispatch interval 30-Oct-2019 22:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
70801RESERVE NOTICE30/10/2019 09:55:09 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 31/10/2019

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs 31/10/2019 to 1600 hrs 31/10/2019.
The forecast capacity reserve requirement is 1488 MW.
The minimum capacity reserve available is 1206 MW.

From 1700 hrs 31/10/2019 to 1730 hrs 31/10/2019.
The forecast capacity reserve requirement is 1474 MW.
The minimum capacity reserve available is 1457 MW.

From 1800 hrs 31/10/2019 to 1830 hrs 31/10/2019.
The forecast capacity reserve requirement is 1443 MW.
The minimum capacity reserve available is 1323 MW.

Manager NEM Real Time Operations
70800MARKET SYSTEMS30/10/2019 03:33:26 PM

CHG0056629 : Apply Change to address performance issues on the EMMS FTP File Server - COMPLETED

Change Number: CHG0056629

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Expedited

Service/ Component: EMMS - Data Interchange

Change Title: Apply Change to address performance issues on the EMMS FTP File Server

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.