67107RECLASSIFY CONTINGENCY04/02/2019 08:29:50 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 04/02/2019 20:29

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 67100

Auto-generated on behalf of Manager NEM Real Time Operations
67106RECLASSIFY CONTINGENCY04/02/2019 07:59:15 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 04/02/2019 19:59 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
67105RECLASSIFY CONTINGENCY04/02/2019 07:59:15 PM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 04/02/2019 19:59 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
67104RECLASSIFY CONTINGENCY04/02/2019 07:54:50 PM

Cancellation of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Cancellation time: 04/02/2019 19:54

Constraint set(s) revoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
V-SA
VIC1-NSW1


Refer AEMO Electricity Market Notice 67099

Auto-generated on behalf of Manager NEM Real Time Operations
67103RECLASSIFY CONTINGENCY04/02/2019 05:34:50 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 04/02/2019 17:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 67096

Auto-generated on behalf of Manager NEM Real Time Operations
67102MARKET SYSTEMS04/02/2019 05:31:32 PM

CHG0052914: API Management Portal Pre-prod DNS records migration.

Change Number: CHG0052914

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: API Management Portal Pre-prod DNS records migration.

Change Start Date & Time: 08/02/2019 10:00:00 AEST

Change End Date & Time: 08/02/2019 14:00:00 AEST

Outage Start Date & Time: 08/02/2019 12:00:00 AEST

Outage End Date & Time: 08/02/2019 14:00:00 AEST

Change Description:

AEMO Preproductuion API portal scheduled maintenance

Environment: Pre-Production

Participant Impact and Requirements:

Users will not be able to login to Preprod API portal during the outage window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
67101MARKET SYSTEMS04/02/2019 05:30:16 PM

CHG0052922: Apply OCT2018 Oracle Security Patch

Change Number: CHG0052922

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: EMMS - Data Store

Change Title: Apply OCT2018 Oracle Security Patch to WARA and FCASA

Change Start Date & Time: 07/02/2019 10:00:00 AEST

Change End Date & Time: 07/02/2019 11:30:00 AEST

Outage Start Date & Time: 07/02/2019 10:00:00 AEST

Outage End Date & Time: 07/02/2019 11:30:00 AEST

Change Description:

Planned System Maintenance on EMMS Pre-Prod Systems.

Environment: Pre-Production

Participant Impact and Requirements:

Maintenance is performed on the EMMS Pre- Production to allow maintenance work.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
67100RECLASSIFY CONTINGENCY04/02/2019 04:27:20 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 04/02/2019 16:27 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
67099RECLASSIFY CONTINGENCY04/02/2019 03:53:10 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Duration: 04/02/2019 15:53 until further notice

Constraint set(s) invoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
V-SA
VIC1-NSW1