Market Notices

71128RECLASSIFY CONTINGENCY12/11/2019 08:40:24 PM

Update - Reclassification of a Non-Credible Contingency Event: Armidale-Dumaresq 8C 330 kV Line and Armidale-Sapphire WF 8E 330 kV Line in NSW1 due to Bushfire.

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notices 71095

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Bushfire. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly, AEMO continues to reclassify it as a credible contingency event.

Region: NSW1

Lines: Armidale-Dumaresq 8C 330 kV Line and Armidale-Sapphire WF 8E 330 kV Line

Duration: 08/11/2019 09:05 until further notice

Constraint set invoked: F-I-BCDM_N-2

Constraint set contains the following interconnector(s) on the left hand side:

NSW1-QLD1
T-V-MNSP1

Manager NEM Real Time Operations
71127RECLASSIFY CONTINGENCY12/11/2019 07:39:40 PM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 12/11/2019 19:39

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 71126

Auto-generated on behalf of Manager NEM Real Time Operations
71126RECLASSIFY CONTINGENCY12/11/2019 06:38:25 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 12/11/2019 18:38 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
71125PRICES UNCHANGED12/11/2019 06:07:04 PM

[EventId:201911121740_confirmed] Prices for interval 12-Nov-2019 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 17:40.

In accordance with Market Notice 71113 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
71124PRICES UNCHANGED12/11/2019 06:06:46 PM

[EventId:201911121805_confirmed] Prices for interval 12-Nov-2019 18:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 18:05.

In accordance with Market Notice 71118 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
71123PRICES UNCHANGED12/11/2019 06:07:20 PM

[EventId:201911121800_confirmed] Prices for interval 12-Nov-2019 18:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 18:00.

In accordance with Market Notice 71117 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
71122PRICES UNCHANGED12/11/2019 06:06:19 PM

[EventId:201911121755_confirmed] Prices for interval 12-Nov-2019 17:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 17:55.

In accordance with Market Notice 71116 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
71121PRICES UNCHANGED12/11/2019 06:05:55 PM

[EventId:201911121750_confirmed] Prices for interval 12-Nov-2019 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 17:50.

In accordance with Market Notice 71115 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
71120PRICES UNCHANGED12/11/2019 06:05:18 PM

[EventId:201911121745_confirmed] Prices for interval 12-Nov-2019 17:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 12 November 2019

PRICES ARE NOW CONFIRMED for dispatch interval 12-Nov-2019 17:45.

In accordance with Market Notice 71114 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.