75350MARKET INTERVENTION15/04/2020 04:08:14 PM

Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 14/04/2020

AEMO ELECTRICITY MARKET NOTICE

Refer Market Notice 75341

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs 15/04/2020.

Manager NEM Real Time Operation
75347MARKET INTERVENTION15/04/2020 01:38:03 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units expected to be synchronised in SA from 0100 hrs to 1530 hrs 16/04/2020 in Pre-dispatch published at 1330 hrs 15/04/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1630 hrs 15/04/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
75346MARKET SYSTEMS15/04/2020 10:49:28 AM

CHG0058784 : Planned System Maintenance - STTM Production Systems

Change Number: CHG0058784
Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Short Term Trading Market

Change Title: Planned System Maintenance - STTM Production Systems

Change Start Date & Time: 23/04/2020 17:30:00 AEST

Change End Date & Time: 23/04/2020 22:30:00 AEST

Outage Start Date & Time: 23/04/2020 18:30:00 AEST

Outage End Date & Time: 23/04/2020 22:30:00 AEST

Change Description:
Maintenance is to be performed on the Production STTM to increase reliability, security and stability of the system. During the maintenance, there will be an outage to the application as per the times mentioned.

Environment: Production

Participant Impact and Requirements:
There will be no access to the Production STTM systems for the duration of the outage. Please access outside these hours.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
75345MARKET SYSTEMS15/04/2020 10:49:48 AM

AEMO Help Desk Bulletin No. 2457 : CHG0058745 - Planned System Maintenance - Electricity MMS Production

Change Number: CHG0058745

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System

Change Title: Planned System Maintenance - Electricity MMS Production

Change Start Date & Time: 21/04/2020 13:00:00 AEST

Change End Date & Time: 21/04/2020 16:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Change Description:
Planned System Maintenance - Electricity MMS Production

Environment: Production

Participant Impact and Requirements:
The maintenance activity is not expected to have any impact on the Production environment however if any issue is identified after the maintenance activity it should be reported to AEMO.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
75344NON-CONFORMANCE15/04/2020 07:30:26 AM

NON-CONFORMANCE Region VIC1 Wednesday, 15 April 2020

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 15 April 2020

AEMO declared a schedule generating unit non-conforming

Unit: YENDWF1
Duration: 15/04/2020 07:05 to 15/04/2020 07:30
Amount: 61 MW
Constraint: NC-V_YENDWF1

Auto-generated on behalf of Manager NEM Real Time Operations
75343RESERVE NOTICE14/04/2020 06:54:40 PM

RESERVE NOTICE MT PASA PUBLICATION 14 April 2020

The MTPASA result published on 14 April 2020 identifies no Low Reserve Conditions.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 75340 published on 14 April 2020.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines

Forecasting
AEMO
75341MARKET INTERVENTION14/04/2020 05:05:01 PM

Direction - SA region - 14/04/2020

AEMO ELECTRICITY MARKET NOTICE.

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1705 hrs on 14/04/2020.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
75340RESERVE NOTICE14/04/2020 03:51:30 PM

RESERVE NOTICE MT PASA PUBLICATION 14 April 2020

The MTPASA result published on 14 April 2020 identifies no Low Reserve Conditions.

The published MTPASA results (run number 267) were simulated on Friday 10th April as there was a technical issue with today's scheduled MTPASA run. An updated MTPASA run will be published later today.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 75233 published on 7 April 2020.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines

Forecasting
AEMO

75339MARKET INTERVENTION14/04/2020 02:47:21 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units expected to be synchronised in SA from 0030 hrs to 1600 hrs 15/04/2020 in Pre-dispatch published at 1430 hrs 14/04/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1700 hrs 14/04/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations