STPASA- Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/05/2022
The Forecast LOR1 conditions in the SA region advised in AEMO Electricity Market Notice No. 96364 have been updated at 1400 hrs 16/05/2022 to the following:
From 1730 hrs to 1830 hrs on 19/05/2022.
The forecast capacity reserve requirement is 376 MW.
The minimum capacity reserve available is 275 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 16/05/2022
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 96385 has been updated at 1430 hrs 16/05/2022 to the following:
[1.] From 1700 hrs 16/05/2022 to 1900 hrs 16/05/2022.
The forecast capacity reserve requirement is 774 MW.
The minimum capacity reserve available is 481 MW.
[2.] From 1700 hrs 17/05/2022 to 1830 hrs 17/05/2022.
The forecast capacity reserve requirement is 783 MW.
The minimum capacity reserve available is 675 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA Region - 14/05/2022
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA Region - 14/05/2022
Refer Market Notice 96329
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs 16/05/2022
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 16/05/2022 13:59
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 96404
Auto-generated on behalf of Manager NEM Real Time Operations
RESERVE NOTICE MT PASA PUBLICATION 17 May 2022
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 96194 published on 10 May 2022.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines
Forecasting
AEMO
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 16/05/2022 11:55 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202205161025_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 16 May 2022 10:25
Issued by Australian Energy Market Operator Ltd at 1025 hrs on 16 May 2022
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 16 May 2022.
Refer to market notice: 96399
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1025 hrs on 16 May 2022.
This is an AEMO autogenerated Market Notice.
[EventId:202205161000_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 16 May 2022 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 16 May 2022
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 16 May 2022.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1000 hrs on 16 May 2022.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 18/05/2022
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 1830 hrs on 18/05/2022.
The forecast capacity reserve requirement is 423 MW.
The minimum capacity reserve available is 382 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.