Stage 4 - Contracts

Having received a complete connection application and agreed to the performance standards, the connecting Network Service Provider (NSP) prepares an offer to connect. The connecting NSP notifies AEMO that a connection agreement has been signed, and provides information required by clause 5.3.7(g) of the National Electricity Rules.

Roles and responsibilities summary

AEMO: AEMO has no involvement at this stage of the process.

NSP: the connecting NSP prepares an offer to connect.

Connection Applicant: executes contracts with connecting NSP.

 

  For more information, you can contact the connecting NSP or email:

  Transmission and distribution connections (NEM advisory) Email us

 

 