Market Notices

119951PRICES SUBJECT TO REVIEW06/11/2024 09:00:17 AM

[EventId:202411060905_review] Prices for interval 06-Nov-2024 09:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 09:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119950RESERVE NOTICE06/11/2024 08:58:04 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119940 is cancelled at 0900 hrs 06/11/2024.

Manager NEM Real Time Operations
     
119949PRICES SUBJECT TO REVIEW06/11/2024 08:55:19 AM

[EventId:202411060900_review] Prices for interval 06-Nov-2024 09:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0855 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 09:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119948PRICES SUBJECT TO REVIEW06/11/2024 08:50:22 AM

[EventId:202411060855_review] Prices for interval 06-Nov-2024 08:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0850 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119947PRICES SUBJECT TO REVIEW06/11/2024 08:46:46 AM

[EventId:202411060850_review] Prices for interval 06-Nov-2024 08:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119946SETTLEMENTS RESIDUE06/11/2024 08:45:21 AM

[EventId:202411060845_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 06 November 2024 08:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Refer to market notice: 119942

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 0845 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119945PRICES SUBJECT TO REVIEW06/11/2024 08:40:20 AM

[EventId:202411060845_review] Prices for interval 06-Nov-2024 08:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0840 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119944PRICES SUBJECT TO REVIEW06/11/2024 08:35:17 AM

[EventId:202411060840_review] Prices for interval 06-Nov-2024 08:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0835 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119943RECLASSIFY CONTINGENCY06/11/2024 08:21:31 AM

Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Duration: 06/11/2024 08:21 until further notice

Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     