Market Notices

118599RECLASSIFY CONTINGENCY04/10/2024 08:50:33 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 04/10/2024 20:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118596RESERVE NOTICE04/10/2024 02:52:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118562 has been updated at 1400 hrs 04/10/2024 to the following:

From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1097 MW.
The minimum capacity reserve available is 855 MW.

AEMO Operations
     
118595MARKET INTERVENTION04/10/2024 03:54:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118565

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 06/10/2024.

The direction update is issued at 1550 hrs 04/10/2024.

Manager NEM Real Time Operations
     
118594MARKET INTERVENTION04/10/2024 03:53:03 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118560

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 06/10/2024.

The direction update is issued at 1550 hrs 04/10/2024.

Manager NEM Real Time Operations
     
118592RECLASSIFY CONTINGENCY03/10/2024 05:51:57 PM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220kV lines in TAS due to bushfire.

AEMO ELECTRICITY MARKET NOTICE

AEMO no longer considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has cancelled the reclassification as a credible contingency event.

Region: TAS

Lines: Farrell - Reece No. 1 and No. 2 220kV lines

Cancellation time: 17:40 hrs 03/10/2024

Constraint set(s) invoked: F-T-FARE_N-2

Refer AEMO Electricity Market Notice 118589

Manager NEM Real Time Operations
     
118591MARKET INTERVENTION03/10/2024 04:33:16 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118565

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/10/2024.

The direction update is issued at 1630 hrs 03/10/2024.

Manager NEM Real Time Operations
     
118590MARKET INTERVENTION03/10/2024 04:31:53 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118560

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/10/2024.

The direction update is issued at 1630 hrs 03/10/2024.

Manager NEM Real Time Operations
     
118589RECLASSIFY CONTINGENCY03/10/2024 02:44:14 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220kV lines in TAS due to bushfire.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220kV lines in TAS due to bushfire.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS

Lines: Farrell - Reece No. 1 and No. 2 220kV lines

Duration: 03/10/2024 1445 hrs until further notice

Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
118588SETTLEMENTS RESIDUE03/10/2024 01:30:30 PM

[EventId:202410031330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 October 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 3 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 October 2024.

Refer to market notice: 118585

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 3 October 2024.

This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm