Filter by category
Filter by Date
[EventId:202411110900_review] Prices for interval 11-Nov-2024 09:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0855 hrs on 11 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 09:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411110855_review] Prices for interval 11-Nov-2024 08:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0850 hrs on 11 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Nov-2024 08:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 0530 hrs 11/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 11/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 11/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120221
Direction is cancelled from: 0530 hrs 11/11/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 0030 hrs 11/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0100 hrs 11/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 11/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120216
Direction is cancelled from: 2345 hrs 10/11/2024
Manager NEM Real Time Operations
[EventId:202411101600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 November 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 10 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 November 2024.
Refer to market notice: 120215
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 10 November 2024.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120194
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 11/11/2024.
The direction update is issued at 1600 hrs 10/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120195
The MINTARO MINTARO GAS direction is now expected to stay in place until 1500 hrs 11/11/2024.
The direction update is issued at 1600 hrs 10/11/2024.
Manager NEM Real Time Operations