Market Notices

120429MARKET INTERVENTION14/11/2024 02:52:58 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 120415

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 15/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 14/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
120428MARKET INTERVENTION14/11/2024 02:51:44 PM

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-3 MURRAY2

Refer AEMO Electricity Participant Notice 120408

The MURR2-3 MURRAY2 direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120427MARKET INTERVENTION14/11/2024 02:50:41 PM

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Snowy Hydro Limited - MURR2-2 MURRAY2

Refer AEMO Electricity Participant Notice 120407

The MURR2-2 MURRAY2 direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120426MARKET INTERVENTION14/11/2024 02:49:20 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB02 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120406

The JLB02 JEERALANG B PO direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120425MARKET INTERVENTION14/11/2024 02:47:55 PM

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - EnergyAustralia Ecogen Pty Ltd - JLB01 JEERALANG B PO

Refer AEMO Electricity Participant Notice 120405

The JLB01 JEERALANG B PO direction is now expected to stay in place until 1630 hrs 14/11/2024.

The direction update is issued at 1445 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120415MARKET INTERVENTION14/11/2024 12:42:44 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 15/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
120412MARKET INTERVENTION14/11/2024 09:53:55 AM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 120381

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 14/11/2024.

The direction update is issued at 0950 hrs 14/11/2024.

Manager NEM Real Time Operations
     
120410RECLASSIFY CONTINGENCY13/11/2024 11:54:10 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 13/11/2024 23:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120409

Auto-generated on behalf of Manager NEM Real Time Operations
     
120409RECLASSIFY CONTINGENCY13/11/2024 10:50:56 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 13/11/2024 22:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     