Filter by category
Filter by Date
[EventId:202411081515_review] Prices for interval 08-Nov-2024 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 8 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Nov-2024 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411081510_review] Prices for interval 08-Nov-2024 15:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 8 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Nov-2024 15:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411081505_review] Prices for interval 08-Nov-2024 15:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 8 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Nov-2024 15:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120103
The MINTARO MINTARO GAS direction is now expected to commence at 2300 hrs 07/11/2024.
The direction update is issued at 1630 hrs 07/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 120077
Direction is cancelled from: 1730 hrs 07/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120097
Direction is cancelled from: 1730 hrs 07/11/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/11/2024
Cancellation - AEMO Intervention Event - SA region 06/11/2024
Refer to Market Notice 120012
The AEMO Intervention Event and all associated directions are cancelled from 1730 hrs on 07/11/2024.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 07/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0130 hrs 08/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 08/11/2024
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 07/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2300 hrs 07/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 09/11/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations