120307GENERAL NOTICE12/11/2024 11:48:51 AM

Project Energy Connect (PEC-1) testing 12th November 2024 1630-2200 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120276

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 16:30hrs to 22:00hrs

This test includes switching of a transmission line in SA and switching of a reactive plant in NSW.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120276GENERAL NOTICE11/11/2024 05:07:24 PM

Project Energy Connect (PEC-1) testing 12th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120016

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 12th November from 06:00hrs to 11:00hrs

This test includes the synchronization of the new PEC Stage 1 interconnector and testing of the Phase Shifting transformer at Buronga substation.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120253INTER-REGIONAL TRANSFER11/11/2024 01:31:43 PM

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bungama - Davenport 275 kV line - SA region - 11/11/2024

At 1307 hrs 11/11/2024 there was an unplanned outage of the Bungama - Davenport 275 kV line.

The following constraint set invoked at 1315 hrs 11/11/2024
S-BGDV

This constraint sets contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120126RESERVE NOTICE07/11/2024 11:49:27 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120120 is cancelled at 2345 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120120RESERVE NOTICE07/11/2024 09:23:02 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 727 MW.
The minimum capacity reserve available is 694 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120099MINIMUM SYSTEM LOAD07/11/2024 03:11:35 PM

Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 07/11/2024.

Refer to Market Notice 119996 for Forecast MSL1.

AEMO Operations
     
120093RESERVE NOTICE07/11/2024 01:17:04 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 8/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120084 is cancelled at 1315 hrs 08/11/2024

Manager NEM Real Time Operations
     
120084RESERVE NOTICE07/11/2024 01:00:43 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1530 hrs 08/11/2024 to 1600 hrs 08/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 735 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120075RESERVE NOTICE07/11/2024 12:27:24 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120059 is cancelled at 1100 hrs 07/11/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     