Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Thursday, 4 April 2024
NON-CONFORMANCE QLD1 Region Thursday, 4 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KAREEYA1
Duration: 04/04/2024 03:00 to 04/04/2024 03:10
Amount: -17 MW
Constraint: NC-Q_KAREEYA1
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 03/04/2024
Non-credible contingency event - QLD region - 03/04/2024
At 2322 hrs the Kareeya PS units 1, 2, 3 and 4 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 03/04/2024
Update - Non-credible contingency event - NSW region - 03/04/2024
Refer AEMO Electricity Market Notice 115944
At 2301 hrs the Eraring Power Station Unit 1 and Unit 2 were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 03/04/2024
Non-credible contingency event - NSW region - 03/04/2024
At 1322 hrs the Eraring Power Station Unit 1 and the Eraring Power Station Unit 2 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 2 April 2024
NON-CONFORMANCE NSW1 Region Tuesday, 2 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 02/04/2024 01:10 to 02/04/2024 01:15
Amount: 34 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 1 April 2024
NON-CONFORMANCE NSW1 Region Monday, 1 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MP1
Duration: 01/04/2024 07:30 to 01/04/2024 07:35
Amount: 19 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 29 March 2024
NON-CONFORMANCE VIC1 Region Friday, 29 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS3
Duration: 29/03/2024 07:55 to 29/03/2024 08:00
Amount: -16 MW
Constraint: NC-V_YWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 28 March 2024
NON-CONFORMANCE VIC1 Region Thursday, 28 March 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS2
Duration: 28/03/2024 17:05 to 28/03/2024 17:10
Amount: -9 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 27/03/2024
Non-credible contingency event - VIC region - 27/03/2024
At 1736 hrs the Terang to Mortlake South 220 kV line opened at the Terang end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations