Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 26/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 922 MW
The minimum capacity reserve available is 706 MW
Manager NEM Real Time Operations
[EventId:202402261745_review] Prices for interval 26-Feb-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402261740_review] Prices for interval 26-Feb-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402261735_review] Prices for interval 26-Feb-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024
Cancellation of Actual (LOR1) condition in the NSW region - 23/02/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.115047 is cancelled at 1645 hrs 23/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 23/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1252 MW
Manager NEM Real Time Operations
[EventId:202402231330_review] Prices for interval 23-Feb-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 23 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402231325_review] Prices for interval 23-Feb-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 23 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402231320_review] Prices for interval 23-Feb-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 23 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Feb-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs