Filter by category
Filter by Date
Non-credible contingency event - SA region - Torrens Island 25/03/2024
Non-credible contingency event - SA region - Torrens Island 25/03/2024
At 1412 hrs there was an unplanned outage of the following elements:
Torrens Island BW3 275 kV CB
Torrens Island BC3 275 kV CB
Torrens Island - Lefevre 275 kV line
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 25/03/2024
Update - Non-credible contingency event - SA region - 25/03/2024
Refer AEMO Electricity Market Notice 115777
At 1350 hrs the Davenport - Brinkworth 275 kV line, Brinkworth No 3 275/132 kV transformer
and Brinkworth - Templers West 275 kV line was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 25/03/2024
Non-credible contingency event - SA region - 25/03/2024
At 0810 hrs there was an unplanned outage of the following elemets:
Davenport - Brinkworth 275 kV line
Brinkworth No 3 275/132 kV transformer
Brinkworth - Templers West 275 kV line
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Severe Space Weather Watch Notification 25/03/2024
Severe Space Weather Watch Notification 25/03/2024
The Australian Bureau of Meteorology's Space Weather Forecasting Centre has issued the following notification.
Severe space weather watch: A recent space weather event is anticipated to impact the Earth within the next 48 hours.
The effects are expected to be significant.
Increased awareness of critical infrastructure is advised.
Please monitor the SWS website for further updates at https://www.sws.bom.gov.au
If required; actions will be taken as per AEMO's system operating procedure SO_OP3715 Power System Security Guidelines.
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 14/03/2024
Update - Non-credible contingency event - SA region - 14/03/2024
Refer AEMO Electricity Market Notice 115624
At 1635 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
[EventId:202403241220_review] Prices for interval 24-Mar-2024 12:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1215 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403241215_review] Prices for interval 24-Mar-2024 12:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1210 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403241210_review] Prices for interval 24-Mar-2024 12:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403241205_review] Prices for interval 24-Mar-2024 12:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.