Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 29/01/2024 to 1830 hrs 29/01/2024.
The forecast capacity reserve requirement is 1470 MW.
The minimum capacity reserve available is 1382 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113842 has been updated at 1700 hrs 27/01/24 to the following:
From 0800 hrs 30/01/2024 to 1600 hrs 30/01/2024.
The forecast capacity reserve requirement is 845 MW.
The minimum capacity reserve available is 516 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113853 is cancelled at 1530 hrs 27/01/2024.
Manager NEM Real Time Operations
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Cancellation - Non-credible contingency event - QLD region - 27/01/2024
Refer AEMO Electricity Market Notice 113825
At 0138 hrs the Gin Gin (H6) No.2 275 kV Busbar tripped.
AEMO has received further information and now determines this was not a non-credible contingency event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113840 has been updated at 1400 hrs to the following:
[From 1900 hrs 27/01/2024 to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 520 MW.
The minimum capacity reserve available is 514 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113829 has been updated at 1400 hrs 27/01/24 to the following:
From 0800 hrs 30/01/2024 to 1300 hrs 30/01/2024.
The forecast capacity reserve requirement is 883 MW.
The minimum capacity reserve available is 505 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113827 has been updated at 1130 hrs to the following:
From 1800 hrs 27/01/2024 to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 520 MW.
The minimum capacity reserve available is 315 MW.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1230 hrs on 27/01/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113828 is cancelled at 1100 hrs 27/01/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 0830 hrs 30/01/2024 to 0900 hrs 30/01/2024.
The forecast capacity reserve requirement is 774 MW.
The minimum capacity reserve available is 709 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations