Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Duration: 16/01/2024 12:31 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Possible intervention to manage power system security in South Australia (SA) Region
Possible intervention to manage power system security in South Australia (SA) Region
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 16/01/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113285 is cancelled at 0700 hrs 16/01/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Cancellation time: 16/01/2024 00:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 113287
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 15/01/2024 22:53 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Cancellation time: 15/01/2024 22:04
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 113281
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers in Qld Region due to Lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following elements. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD
Elements: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers
Cancellation time : 1910 hrs 15/01/2024
Constraint set(s) revoked: Q-MR_TX2_3_N-2
Refer AEMO Electricity Market Notice 113273
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV
Cancellation time: 15/01/2024 18:54
Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 113282
Auto-generated on behalf of Manager NEM Real Time Operations