120051RESERVE NOTICE07/11/2024 02:46:44 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120047 is cancelled at 0245 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120047RESERVE NOTICE07/11/2024 01:19:03 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120044 has been updated at 0100 hrs to the following:

[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 702 MW.
The minimum capacity reserve available is 684 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120044RESERVE NOTICE06/11/2024 09:10:03 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 747 MW.
The minimum capacity reserve available is 589 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120016GENERAL NOTICE06/11/2024 04:57:21 PM

Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119963

The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.

Terry Liu
AEMO Operations
     
120004SETTLEMENTS RESIDUE06/11/2024 03:21:45 PM

[EventId:202411061520_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 06 November 2024 15:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Refer to market notice: 119986

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 1520 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119994SETTLEMENTS RESIDUE06/11/2024 02:47:19 PM

[EventId:202411061445_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 06 November 2024 14:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Refer to market notice: 119973

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1445 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119986SETTLEMENTS RESIDUE06/11/2024 02:36:33 PM

[EventId:202411061435_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1435 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119973SETTLEMENTS RESIDUE06/11/2024 02:05:18 PM

[EventId:202411061405_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 06 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1405 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119963GENERAL NOTICE06/11/2024 11:27:15 AM

Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119961

This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.

The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.