Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 12/11/2024 19:36 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 12/11/2024 18:54
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 120319
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 12/11/2024 18:49
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 120318
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line in VIC due to lightning.
Reclassification of a non-credible contingency event as a credible contingency event due to lightning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC
Lines: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line
Duration: 12/11/2024 18:15 hrs until further notice
Constraint set(s) invoked: V-ROYP78_R_N-2
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 12/11/2024 17:59
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120320
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 12/11/2024 15:58 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 12/11/2024 15:51 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Duration: 12/11/2024 15:45 until further notice
Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 12/11/2024 15:44
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 120311
Auto-generated on behalf of Manager NEM Real Time Operations