[EventId:202401160700_review] Prices for interval 16-Jan-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 16 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jan-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 18/01/2024 to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 1242 MW.
The minimum capacity reserve available is 1109 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 19/01/2024.
The forecast capacity reserve requirement is 1253 MW.
The minimum capacity reserve available is 1161 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 1247 MW.
The minimum capacity reserve available is 985 MW.
AEMO Operations
INC0124489 | RESOLVED | Issue with PD-PASA runs
SERVICE INTERRUPTION - RESOLVED
Please be informed that we had issue with Pre-Dispatch Projected Assessment of System Adequacy (PDPASA) service which has been restored now.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
CHG0082517 | Production | Prod MSATS 50.0.4 LCCD Defect Release | CANCELLED
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Prod MSATS 50.0.4 LCCD Defect Release
Change Start Date & Time: 21/01/2024 10:00:00 AEST
Change End Date & Time: 21/01/2024 17:00:00 AEST
Outage Start Date & Time: 21/01/2024 10:00:00 AEST
Outage End Date & Time: 21/01/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024
Inter-regional transfer limit variation - South East CB6611 - SA region - 11/01/2024
At 0955 hrs 11/01/2024 there was an short notice outage of South East CB6611.
The following constraint set(s) invoked at 0955 hrs 11/01/2024
S-SECB6611_10
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 10 January 2024
NON-CONFORMANCE NSW1 Region Wednesday, 10 January 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 10/01/2024 00:15 to 10/01/2024 00:30
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations