Filter by category
Filter by Date
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 1029 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1244 MW.
The minimum capacity reserve available is 1180 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113582 has been updated at 1100 hrs to the following:
[1.] From 1830 hrs 22/01/2024 to 2000 hrs 22/01/2024.
The forecast capacity reserve requirement is 1100 MW.
The minimum capacity reserve available is 690 MW.
Manager NEM Real Time Operations
[EventId:202401221100_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 22 January 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1100 hrs on 22 January 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202401212140_review] Prices for interval 21-Jan-2024 21:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 2135 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401212135_review] Prices for interval 21-Jan-2024 21:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401212130_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 21 January 2024 21:30
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 21 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 21 January 2024.
Refer to market notice: 113580
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 2130 hrs on 21 January 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202401212130_review] Prices for interval 21-Jan-2024 21:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 2125 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401212125_review] Prices for interval 21-Jan-2024 21:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 2120 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.