Market Notices

115671INTER-REGIONAL TRANSFER17/03/2024 04:56:22 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 17/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 17/03/2024

A planned outage of Red Cliffs - Buronga 0X1 220 kV Line in the Vic region was scheduled from 0500 hrs 17/03/2024 to 1900 hrs 17/03/2024.

The outage has been completed and returned to service at 1655 hrs 17/03/2024.

Constraint set(s) revoked:
I-BURC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115663INTER-REGIONAL TRANSFER16/03/2024 05:12:33 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 16/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga 0X1 220 kV Line - Vic region - 16/03/2024

A planned outage of Red Cliffs - Buronga 0X1 220 kV Line in the Vic region was scheduled from 0500 hrs 16/03/2024 to 1900 hrs 16/03/2024.

The outage has been completed and returned to service at 1655 hrs 16/03/2024.

Constraint set(s) revoked:
I-BURC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115652INTER-REGIONAL TRANSFER15/03/2024 02:52:51 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 1445 hrs 15/03/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
115627INTER-REGIONAL TRANSFER15/03/2024 06:31:39 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

At 0600 hrs 15/03/2024 there was a short notice outage of Robertstown - Tungkillo No. 2 275 kV Line.
At 0615 hrs 15/03/2024 there was a short notice outage of Tungkillo - Para No. 1 275 kV Line.

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505DC4C from 06:00 hrs until further notice

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115626INTER-REGIONAL TRANSFER15/03/2024 05:10:47 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024

In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.

CA_SYDS_5505D0BC from 04:40 hrs to 05:10 hrs
CA_SYDS_5505D516 from 04:55 hrs to 05:10 hrs

These constraint sets contains equations with the following interconnector on the LHS;

V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115625INTER-REGIONAL TRANSFER14/03/2024 11:49:03 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024

At 2307 hrs 14/03/2024 there was an unplanned outage of Robertstown - Tungkillo No. 1 275 kV Line.


The following constraint set(s) invoked at 2315 hrs 14/03/2024
S-RBTU

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115624POWER SYSTEM EVENTS14/03/2024 11:47:59 PM

Non-credible contingency event - SA region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 14/03/2024

At 2307 hrs the Tungkillo - Robertstown No. 1 275 kV Line and the Tungkillo East 275 kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
115618INTER-REGIONAL TRANSFER14/03/2024 07:32:14 AM

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024

At 0800 hrs 14/03/2024 there was a short notice outage of Lismore 132kV SVC.

The following constraint set(s) invoked at 0800 hrs 14/03/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
115595POWER SYSTEM EVENTS12/03/2024 03:29:42 AM

Non-credible contingency event - QLD region - 12/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/03/2024

At 0249 hrs the Strathmore - Clare South No 7208 132KV Line opened at Strathmore end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations