Market Notices

114937MARKET SYSTEMS22/02/2024 09:56:46 AM

CHG0085737 | Pre-Production | Pre-production EMMS database refresh

Change Number: CHG0085737
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Pre-production EMMS database refresh
Change Start Date & Time: 26/02/2024 08:00:00 AEST
Change End Date & Time: 17/03/2024 17:30:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: The pre-production EMMS environment will be refreshed with production data (NEM, WARE, SETTLEMENTS & GSH databases).
The Electricity Market Management System (EMMS) and Gas Supply Hub (GSH) Pre-Production environment will be unavailable during the outage window.

Upon completion of the outage users will be required to log in to the GSH Trayport application using their Production credentials.Trayport passwords in Pre-Production environment will be replaced with their Production passwords
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114936SETTLEMENTS RESIDUE22/02/2024 09:00:27 AM

[EventId:202402220900_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 February 2024 09:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0900 hrs on 22 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0900 hrs on 22 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114935SETTLEMENTS RESIDUE22/02/2024 08:00:15 AM

[EventId:202402220800_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 22 February 2024 08:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 22 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Refer to market notice: 114934

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 0800 hrs on 22 February 2024.

This is an AEMO autogenerated Market Notice.
114934SETTLEMENTS RESIDUE22/02/2024 06:35:20 AM

[EventId:202402220635_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 February 2024 06:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0635 hrs on 22 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0635 hrs on 22 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114928SETTLEMENTS RESIDUE21/02/2024 07:15:16 PM

[EventId:202402211915_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 21 February 2024 19:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1915 hrs on 21 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 21 February 2024.

Refer to market notice: 114926

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.

The negative residue constraint NRM_SA1_VIC1 ceased operating at 1915 hrs on 21 February 2024.

This is an AEMO autogenerated Market Notice.
114926SETTLEMENTS RESIDUE21/02/2024 06:25:39 PM

[EventId:202402211825_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 21 February 2024 18:25

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 21 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 21 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1825 hrs on 21 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
114917RESERVE NOTICE21/02/2024 02:56:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1251 MW.
The minimum capacity reserve available is 1076 MW.

AEMO Operations
114915SETTLEMENTS RESIDUE21/02/2024 11:30:29 AM

[EventId:202402211130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 February 2024 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 21 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 February 2024.

Refer to market notice: 114914

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1130 hrs on 21 February 2024.

This is an AEMO autogenerated Market Notice.
114914SETTLEMENTS RESIDUE21/02/2024 09:55:25 AM

[EventId:202402210955_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 February 2024 09:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0955 hrs on 21 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0955 hrs on 21 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm