Filter by category
Filter by Date
[EventId:202410141830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 October 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 14 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 October 2024.
Refer to market notice: 118886
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 14 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410141735_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 October 2024 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 14 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1735 hrs on 14 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410131330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 October 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 13 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 October 2024.
Refer to market notice: 118839
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 13 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410131045_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 October 2024 10:45
Issued by Australian Energy Market Operator Ltd at 1045 hrs on 13 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1045 hrs on 13 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410130700_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 13 October 2024 07:00
Issued by Australian Energy Market Operator Ltd at 0700 hrs on 13 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 13 October 2024.
Refer to market notice: 118831
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0700 hrs on 13 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410130000_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 13 October 2024 00:00
Issued by Australian Energy Market Operator Ltd at 0000 hrs on 13 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 13 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 0000 hrs on 13 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410121530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 October 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 12 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 October 2024.
Refer to market notice: 118827
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 12 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410121405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 October 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 12 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 12 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410121230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 October 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 12 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 October 2024.
Refer to market notice: 118807
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 12 October 2024.
This is an AEMO autogenerated Market Notice.