Update - Direction - SA Region - 24/01/2024
Update - Direction - SA Region - 24/01/2024
Refer Market Notice 113710
The AEMO intervention event that commenced from interval ending 1635 hrs on 24/01/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113854 has been updated at 1530 hrs to the following:
From 1730 hrs 27/01/2024 to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 1033 MW.
The minimum capacity reserve available is 530 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113853 is cancelled at 1530 hrs 27/01/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1400 hrs 30/01/2024 to 1600 hrs 30/01/2024.
The forecast capacity reserve requirement is 840 MW.
The minimum capacity reserve available is 640 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/12/2023
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1530 hrs 29/01/2024 to 1600 hrs 29/01/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 1167 MW.
[2.] From 1630 hrs 29/01/2024 to 2030 hrs 29/01/2024.
The forecast capacity reserve requirement is 1252 MW.
The minimum capacity reserve available is 1068 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 28/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
From 1700 hrs 28/01/2024 to 2130 hrs 28/01/2024.
The forecast capacity reserve requirement is 1066 MW.
The minimum capacity reserve available is 977 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113785 has been updated at 1400 hrs to the following:
[1.] From 1700 hrs 27/01/2024 to 1900 hrs 27/01/2024.
The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 583 MW.
[2.] From 1930 hrs 27/01/2024 to 2200 hrs 27/01/2024.
The forecast capacity reserve requirement is 1009 MW.
The minimum capacity reserve available is 540 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113840 has been updated at 1400 hrs to the following:
[From 1900 hrs 27/01/2024 to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 520 MW.
The minimum capacity reserve available is 514 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
INTENTION TO IMPLEMENT an AEMO INTERVENTION EVENT WITH RERT
AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) - QLD1 Region - 27/01/2024
Refer to AEMO Electricity Market Notice no. 113841.
AEMO has entered into a reserve contract and may implement a AEMO Intervention Event by dispatching that reserve contract to maintain the power system in a Reliable operating state during the following period of time;
17:30 to 21:00 hrs 27/01/2024
If reserve is required, the period of activation or dispatch will be within this period, but may not be for all the entire period.
AEMO will issue a further advice if the reserve contract is dispatched/activated.
Manager NEM Real Time Operations