[EventId:202402261745_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 26 February 2024 17:45
Issued by Australian Energy Market Operator Ltd at 1746 hrs on 26 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 26 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1745 hrs on 26 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402261745_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 February 2024 17:45
Issued by Australian Energy Market Operator Ltd at 1746 hrs on 26 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1745 hrs on 26 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402261750_review] Prices for interval 26-Feb-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1746 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402261745_review] Prices for interval 26-Feb-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402261740_review] Prices for interval 26-Feb-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115135 has been updated at 1740 hrs 26/02/2024 to the following:
[1.] From 1430 hrs 29/02/2024 to 1930 hrs 29/02/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 243 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202402261735_review] Prices for interval 26-Feb-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 26 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 26-Feb-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
[1.] From 1730 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 729 MW.
The minimum capacity reserve available is 355 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202402261500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 February 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 26 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 February 2024.
Refer to market notice: 115133
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 26 February 2024.
This is an AEMO autogenerated Market Notice.