114016RESERVE NOTICE30/01/2024 03:15:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 476 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113995SETTLEMENTS RESIDUE29/01/2024 06:20:18 PM

[EventId:202401291820_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 January 2024 18:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1820 hrs on 29 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 January 2024.

Refer to market notice: 113992

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1820 hrs on 29 January 2024.

This is an AEMO autogenerated Market Notice.
113993SETTLEMENTS RESIDUE29/01/2024 05:55:30 PM

[EventId:202401291755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 January 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 29 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2024.

Refer to market notice: 113985

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 29 January 2024.

This is an AEMO autogenerated Market Notice.
113992SETTLEMENTS RESIDUE29/01/2024 05:56:27 PM

[EventId:202401291755_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 January 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 29 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1755 hrs on 29 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113985SETTLEMENTS RESIDUE29/01/2024 04:30:21 PM

[EventId:202401291630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 January 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 29 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 29 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113983NON-CONFORMANCE29/01/2024 04:05:13 PM

NON-CONFORMANCE Region NSW1 Monday, 29 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 29/01/2024 16:00 to 29/01/2024 16:05
Amount: 66 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
113980RESERVE NOTICE29/01/2024 03:39:05 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113977 is cancelled at 1500 hrs 29/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
113977RESERVE NOTICE29/01/2024 03:20:32 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113968 has been updated at 1400 hrs 29/01/2024 to the following:

From 0800 hrs to 1400 hrs 01/02/2024.
The forecast capacity reserve requirement is 910 MW.
The minimum capacity reserve available is 29 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113972MARKET INTERVENTION29/01/2024 04:18:46 PM

Update - Direction - SA Region - 28/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 28/01/2024

Refer Market Notice 113930

The AEMO intervention event that commenced from interval ending 1705 hrs on 28/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm