Filter by category
Filter by Date
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119875
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1600 hrs 06/11/2024.
The direction update is issued at 1530 hrs 05/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119875
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 06/11/2024.
The direction update is issued at 1530 hrs 05/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119875
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 2200 hrs 05/11/2024 direction is now expected to stay in place until 0400 hrs 06/11/2024.
The direction update is issued at 1230 hrs 05/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119887
Direction is cancelled from: 1030 hrs 05/11/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119878
The TORRB4 TORRENS ISLAN unit is now expected to synchronise at 2330 hrs 05/11/2024 direction is now expected to stay in place until 0400 hrs 06/11/2024.
The direction update is issued at 0900 hrs 05/11/2024.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119875
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 2130 hrs 04/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0730 hrs 05/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 05/11/2024
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 29/10/2024
Cancellation - AEMO Intervention Event - SA region 29/10/2024
Refer to Market Notice 119651
The AEMO Intervention Event and all associated directions are cancelled from 1700 hrs on 04/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 119848
Direction is cancelled from: 1700 hrs 04/11/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119847
Direction is cancelled from: 1630 hrs 04/11/2024
Manager NEM Real Time Operations