Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 09/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024
Refer Market Notice 116510
The AEMO Intervention Event and all associated directions are cancelled from 0805 hrs 08/05/2024
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region [beginning] on 08/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116519 is cancelled at 0615 hrs 08/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 0700 hrs 08/05/2024 to 0730 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1357 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116506 is cancelled at 2015 hrs 07/05/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1366 MW
Manager NEM Real Time Operations
Direction - {{REGION:SA}} region {{DATE:07/05/2024}}
Direction - {{REGION:SA}} region {{DATE:07/05/2024}}
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the {{REGION:SA}} region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending {{HRS:1605}} hrs on {{DATE:07/05/2024}}.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116505
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 08/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 07/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations