Market Notices

115433MARKET INTERVENTION02/03/2024 02:02:13 PM

Direction - SA region 02/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 02/03/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1405 hrs on 02/03/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115430MARKET INTERVENTION02/03/2024 10:32:24 AM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0130 hrs 03/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 02/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115423MARKET INTERVENTION01/03/2024 05:04:18 PM

Direction - SA region 01/03/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 01/03/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 01/03/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115418MARKET INTERVENTION01/03/2024 03:36:33 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 29/02/2024

Refer Market Notice 115364

The AEMO Intervention Event and all associated directions are cancelled from 1535 hrs 01/03/2024

Manager NEM Real Time Operations
115414MARKET INTERVENTION01/03/2024 03:01:28 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115403

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 02/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 01/03/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115413GENERAL NOTICE01/03/2024 02:45:46 PM

Update - Lightning vulnerable equipment in QLD region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable equipment in QLD region

Special Reclassification of Transmission Equipment during lightning

Refer to AEMO Electricity Market Notice 115270.

At 1029 hrs 28/02/2024 the Tully - Cardwell No.7389 132 kV Line tripped and auto reclosed and Ross - Woree No. 8905 275 kV Line tripped and auto reclosed.

The cause of the trip was identified as due to lightning.

In accordance with SO_OP_3715, AEMO now considers these lines to be vulnerable due to lightning.

Manager NEM Real Time Operations
115403MARKET INTERVENTION01/03/2024 12:21:07 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 02/03/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
115364MARKET INTERVENTION29/02/2024 04:46:21 PM

Direction - SA region 29/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 29/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 29/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
115361MARKET INTERVENTION29/02/2024 02:11:33 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 115359

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 01/03/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 29/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations