[EventId:202411011040_review] Prices for interval 01-Nov-2024 10:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 1 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-Nov-2024 10:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411011035_review] Prices for interval 01-Nov-2024 10:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1030 hrs on 1 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-Nov-2024 10:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - NSW region - 31/10/2024
Update - Non-credible contingency event - NSW region - 31/10/2024
Refer AEMO Electricity Market Notice 119689
At 0345 hrs the Wagga B 330 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 31/10/2024
Non-credible contingency event - NSW region - 31/10/2024
At 0028 hrs the Wagga B 330 kV bus tripped which offloaded the Wagga - Walla Walla SF 6Y 330 kV line and Wagga No.3 transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 05/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 05/11/2024.
Minimum regional demand is forecast to be 1238 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1535 MW
MSL2 - 1035 MW
MSL3 - 535 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1400 hrs 05/11/2024.
AEMO Operations
[EventId:202410301355_review] Prices for interval 30-Oct-2024 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 30 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Oct-2024 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410301350_review] Prices for interval 30-Oct-2024 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 30 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Oct-2024 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410301345_review] Prices for interval 30-Oct-2024 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 30 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Oct-2024 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202410301340_review] Prices for interval 30-Oct-2024 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 30 October 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 30-Oct-2024 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.