119860RESERVE NOTICE04/11/2024 02:17:31 PM

STPASA - Update for the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119849 has been updated at 1300 hrs to the following:

1. From 1300 hrs to 1330 hrs 07/11/2024.
The forecast capacity reserve requirement is 1191 MW.
The minimum capacity reserve available is 963 MW.

2. From 1430 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 269 MW.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 06/11/2024.


AEMO Operations
     
119853RESERVE NOTICE04/11/2024 08:07:08 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119834 has been updated at 0800 hrs to the following:

[1.] From 1730 hrs 04/11/2024 to 1930 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 788 MW.

Manager NEM Real Time Operations
     
119852MINIMUM SYSTEM LOAD04/11/2024 08:53:24 AM

Forecast Minimum System Load MSL2 condition in the VIC region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 = 1760 MW
- MSL2 = 1260 MW
- MSL3 = 760 MW

The regional demand is forecast to be below the MSL2 threshold for the following period:

From 1230 hrs 10/11/2024 to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1236 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.

AEMO is seeking a market response.


AEMO Operations
     
119851RESERVE NOTICE04/11/2024 08:54:46 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119842 has been updated at 0800 hrs to the following:

From 1700 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 118 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
119850RESERVE NOTICE04/11/2024 08:56:03 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 119842 has been updated at 0800 hrs to the following:

From 1800 hrs to 1900 hrs 06/11/2024.
The forecast capacity reserve requirement is 849 MW.
The minimum capacity reserve available is 565 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
119849RESERVE NOTICE04/11/2024 08:57:21 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119843 has been updated at 0800 hrs to the following:

From 1330 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 113 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
119846RESERVE NOTICE04/11/2024 08:58:40 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119843 has been updated at 0800 hrs to the following:

From 1700 hrs to 2000 hrs 06/11/2024.
The forecast capacity reserve requirement is 1393 MW.
The minimum capacity reserve available is 555 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
119843RESERVE NOTICE04/11/2024 07:14:51 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 119838 has been updated at 0700 hrs 04/11/2024 to the following:

[1.] From 1700 hrs 06/11/2024 to 2000 hrs 06/11/2024.
The forecast capacity reserve requirement is 1372 MW.
The minimum capacity reserve available is 473 MW.

[2.] From 1400 hrs 07/11/2024 to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 25 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
119842RESERVE NOTICE04/11/2024 07:13:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region beginning on 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:

[1.] From 1730 hrs 06/11/2024 to 1900 hrs 06/11/2024.
The forecast capacity reserve requirement is 824 MW.
The minimum capacity reserve available is 487 MW.

[2.] From 1700 hrs 07/11/2024 to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 535 MW.
The minimum capacity reserve available is 30 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm