Market Notices

119015RECLASSIFY CONTINGENCY17/10/2024 10:39:37 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Cancellation time: 2230 hrs 17/10/2024
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 119000

Manager NEM Real Time Operations
     
119014RECLASSIFY CONTINGENCY17/10/2024 10:38:41 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 2230 hrs 17/10/2024
Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 118937

Manager NEM Real Time Operations
     
119013RECLASSIFY CONTINGENCY17/10/2024 10:37:33 PM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 118994 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 2230 hrs 17/10/2024.

Constraint set(s) revoked:
I-VS_250

Manager NEM Real Time Operations
     
119000RECLASSIFY CONTINGENCY17/10/2024 07:52:01 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 1950 hrs 17/10/2024 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
118999RECLASSIFY CONTINGENCY17/10/2024 07:29:11 PM

Cancellation of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Cancellation time: 17/10/2024 19:29

Constraint set(s) revoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 118988

Auto-generated on behalf of Manager NEM Real Time Operations
     
118995RESERVE NOTICE17/10/2024 06:41:36 PM

Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 17/10/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.118993 is cancelled at 1839 hrs 17/10/2024.

Manager NEM Real Time Operations
     
118994RECLASSIFY CONTINGENCY17/10/2024 06:33:15 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - SA region

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely destructive winds in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

AEMO has taken the following action(s) to maintain power system security at 1830hrs 17/10/2024.
Constraint set(s) invoked:
I-VS_250
Duration: 1830 hrs until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
     
118993RESERVE NOTICE17/10/2024 06:19:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 17/10/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1136 MW
The minimum capacity reserve available is 1076 MW

Manager NEM Real Time Operations
     
118992RECLASSIFY CONTINGENCY17/10/2024 04:29:11 PM

Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Cancellation time: 17/10/2024 16:29

Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 118989

Auto-generated on behalf of Manager NEM Real Time Operations
     