Filter by category
Filter by Date
NEM Local Temperature Alerts for SA, VIC from 09 Feb 2024 to 13 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
VIC
Mildura Ap (39+ Deg C): 12th Feb, 13th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update - Direction - SA Region - 04/02/2024
Update - Direction - SA Region - 04/02/2024
Refer Market Notice 114245
The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA from 08 Feb 2024 to 12 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Feb, 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Update - Direction - SA Region - 04/02/2024
Update - Direction - SA Region - 04/02/2024
Refer Market Notice 114245
The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
QNI Minor testing (NSW to Qld) 7th February 2024
Refer to market notice 113265
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Wednesday 7th February 2024 from 1400 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Update - Direction - SA Region - 04/02/2024
Update - Direction - SA Region - 04/02/2024
Refer Market Notice 114245
The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Fast Frequency Response Market - Increase in L1 FCAS dispatch cap from 12 February 2024.
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 12 Febraury AEMO will:
Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 100 MW to 125 MW
Retain the cap on dispatch of Very Fast Raise (R1) Contingency FCAS at 225 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
Update - Direction - SA Region - 04/02/2024
Update - Direction - SA Region - 04/02/2024
Refer Market Notice 114245
The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114291 is cancelled at 1245 hrs 05/02/2024.
Manager NEM Real Time Operations