Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118155
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/09/2024.
The direction update is issued at 1600 hrs 06/09/2024.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/09/2024
Non-credible contingency event - VIC region - 06/09/2024
At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
CHG0098106 | Completed | Production | EMMS Production Bay transfer
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0097007 | Cancelled | Production | AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0097010 | Cancelled | Production | AEMO will be undertaking maintenance activities on the RCM system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the RCM system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0097011 | Cancelled | Production | AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the EMMS - MATRIXIDR,Stpasa system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118126
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/09/2024.
The direction update is issued at 1630 hrs 05/09/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 118125
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/09/2024.
The direction update is issued at 1630 hrs 05/09/2024.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - NSW region 05/09/2024
Cancellation - AEMO Intervention Event - NSW region 05/09/2024
Refer to Market Notice 118153
The AEMO Intervention Event and all associated directions are cancelled from 1440 hrs on 05/09/2024.
Manager NEM Real Time Operations