Notifications of Facility retirements

The Minister for Energy amended the Wholesale Electricity Market (WEM) Rules on 11 February 2020 to implement changes to the Reserve Capacity Price from the 2019 Reserve Capacity Cycle. As part of these changes, a Market Participant is required to provide three years’ notice of a Facility ceasing operations permanently. AEMO must publish the details of the retirement on the Market Website.

AEMO considers the following notices to be notifications under clause 4.4A.1 of the WEM Rules:

  • On 11 April 2022, Landfill Gas and Power Pty Ltd notified AEMO that it intends to retire KALAMUNDA_SG.
  • On 28 October 2021, Synergy notified AEMO that it intends to retire PPP_KCP_EG1 and PPP_KCP_IL1.
  • On 26 March 2020, Synergy notified AEMO that it intends to retire MUJA_G5 and MUJA_G6.

In accordance with clause 4.4A.2 of the WEM Rules, the relevant details can be found in the table below. 

Facility

Capacity Credits (MW)

Relevant Capacity Year

Standing Data nameplate capacity (MW)

Transmission Node Identifier

 Latitude

 Longitude

Expected closure date

 KALAMUNDA_SG

1.300

2021-22

 1.3

WKDA

 -31.97

 116.00

1 July 2022

 PPP_KCP_EG1

80.400

2021-22

 116.0

WMSR - Mason Road

 -31.95

 115.86

1 December 2021

 PPP_KCP_IL1

N/A

2021-22

 N/A

WMSR - Mason Road

 -31.95

 115.86

1 December 2021

MUJA_G5

195.000

2019-20

195.8

 N/A

 N/A

 N/A

1 October 2022

MUJA_G6

193.000

2019-20

193.6

 N/A

 N/A

 N/A

1 October 2024

X