2024 Metering Services Review Package 1

18/12/2024
Market National Electricity Market
StageFinal Report
ConvenorAEMO NEM
Initiated29/05/2024
Accepting submissions?No

On 28 November 2024, the Australian Energy Market Commission (AEMC) published a final rule to achieve universal smart meter deployment in the NEM by 2030. The final rule introduces a package of reforms designed to accelerate the deployment of smart meters and unlock the benefits of smart meter data.

AEMO has concluded its consultation on the Retail Electricity Market Procedures under the National Electricity Rules (NER). The consultation focused on changes to AEMO's MSATS procedures regarding Legacy Meter Replacement Plans and Defect management, designed to accelerate the deployment of smart meters.

Other matters addressed in this Final Report include:

  • The AEMO review of the processes for Retailers of Last Resort (RoLR).
  • Issues and Change Forms (ICFs) raised by the ERCF.
  • Anomalies in Embedded Network settlements.

This consultation was consulted in accordance with the Rules consultation requirements detailed in clause 8.9 of the National Electricity Rules.

For queries, please contact: NEM.Retailprocedureconsultations@aemo.com.au

  • First stage
  • Second stage
  • Final stage

Metering Services Review

AEMO review of the processes for Retailers of Last Resort (RoLR)

Procedure Type of Change  Date
NEM RoLR Processes Part A and Part B v2.51 (change marked).pdf   Amendment  1 December 2025

ICF-077 Auto population of the LCCD based on NMI status


ICF-078 Alignment of Addressing in B2M Procedures to AS4590.1:2017

ICF-079 NEM12 MDFF Inconsistencies

Procedure Type of Change Date
MDFF Specification NEM12 NEM13 v2.7 (change marked) draft.pdf Amendment 1 December 2025

Embedded Network Settlement Anomalies

Metering Services Review

Procedure  Type of Change  Proposed effective date Links
MSATS Procedures - Principles and Obligations for All Connection Points v7   Amendment 26 October 2025 Change Marked
Clean
Standing Data for MSATS v6.1   Amendment 26 October 2025 Change Marked
Clean
MSATS Procedures - Principles and Obligations for All Connection Points v7.1   Amendment 1 December 2025 Change Marked
Clean
Standing Data for MSATS v6.2 Amendment 1 December 2025 Change Marked
Clean
Retail Electricity Market Procedures – Glossary and Framework v4.4 Amendment 1 December 2025 Change Marked
Clean

AEMO review of the processes for Retailers of Last Resort (RoLR)

Procedure  Type of Change  Proposed effective date Links
NEM RoLR Processes Part A and Part B v2.5 Amendment 1 December 2025 Change Marked
Clean

ICF-077 Auto population of the LCCD based on NMI status

Procedure  Type of Change  Proposed effective date Links
MSATS Procedures - Principles and Obligations for All Connection Points v7.1   Amendment 1 December 2025 Change Marked
Clean
Retail Electricity Market Procedures – Glossary and Framework v4.4 Amendment 1 December 2025 Change Marked
Clean

ICF-078 Alignment of Addressing in B2M Procedures to AS4590.1:2017

Procedure  Type of Change  Proposed effective date Links
MSATS Procedures - Principles and Obligations for All Connection Points v7.1   Amendment 1 December 2025 Change Marked
Clean
Standing Data for MSATS v6.2 Amendment 1 December 2025 Change Marked
Clean

ICF-079 NEM12 MDFF Inconsistencies

Procedure  Type of Change  Proposed effective date Links
MDFF Specification NEM12 NEM13 v2.7   Amendment 1 December 2025 Change Marked
Clean

Embedded Network Settlement Anomalies

Procedure  Type of Change  Proposed effective date Links
MSATS Procedures - Principles and Obligations for All Connection Points v7.1 Amendment 1 December 2025 Change Marked
Clean