118297RESERVE NOTICE16/09/2024 05:42:56 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 16/09/2024 to 1830 hrs 16/09/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1362 MW.

Manager NEM Real Time Operations
     
118296RESERVE NOTICE17/09/2024 01:13:10 PM

RESERVE NOTICE MT PASA PUBLICATION 17 September 2024

The MTPASA result published on 17 September 2024 identifies Low Reserve Conditions as annual unserved energy exceeds the Reliability Standard between:
-- September 2024 - September 2025 in South Australia.

AEMO declares low reserve conditions in accordance with clause 4.8.4 of the National Electricity Rules for the following region(s) and periods:
-- January 2025 - March 2025 in South Australia when forecast demand exceeds supply under some circumstances.

Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.

For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy

This notice supersedes Market Notice 118203 published on 10 September 2024.

Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/Electricity/National

Forecasting
AEMO
     
118295RESERVE NOTICE16/09/2024 04:27:43 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118280 is cancelled at 1600 hrs 16/09/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
118294MARKET INTERVENTION16/09/2024 05:00:35 PM

Direction - SA region 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 16/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1705 hrs on 16/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118293MARKET INTERVENTION16/09/2024 04:58:57 PM

Direction - SA region 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 16/09/2024

Refer to Market Notice 118291


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1700 hrs 16/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0800 hrs 17/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 1630 hrs 17/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118292MARKET INTERVENTION16/09/2024 04:57:49 PM

Direction - SA region 16/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 16/09/2024

Refer to Market Notice 118291


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1700 hrs 16/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0830 hrs 17/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 1600 hrs 17/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118291MARKET INTERVENTION16/09/2024 02:52:05 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118289

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 17/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 16/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118290RECLASSIFY CONTINGENCY16/09/2024 01:14:54 PM

Cancellation of Reclassification of a Non-Credible Contingency Event - QLD region - 30/04/2019

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Reclassification of a Non-Credible Contingency Event: Nebo SVC and the Nebo No.2 275/132kV transformer - QLD region - 30/04/2019.

Refer AEMO Electricity Market Notice 68251

Based on advice from the participant, AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.


Region: QLD

Equipment: Nebo SVC and the Nebo No.2 275/132kV transformer

Cancellation time: 1315 hrs 16/09/2024

Constraint set(s) revoked: Nil


Manager NEM Real Time Operations
     
118289MARKET INTERVENTION16/09/2024 12:53:03 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 17/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     