Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 26/03/2025 17:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125957
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 26/03/2025 17:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125956
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503261640_confirmed] Prices for interval 26-Mar-2025 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 16:40.
In accordance with Market Notice 125966 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503261700_confirmed] Prices for interval 26-Mar-2025 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 17:00.
In accordance with Market Notice 125970 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503261655_confirmed] Prices for interval 26-Mar-2025 16:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 16:55.
In accordance with Market Notice 125969 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503261650_confirmed] Prices for interval 26-Mar-2025 16:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 16:50.
In accordance with Market Notice 125968 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503261645_confirmed] Prices for interval 26-Mar-2025 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 16:45.
In accordance with Market Notice 125967 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503261635_confirmed] Prices for interval 26-Mar-2025 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 26 March 2025
PRICES ARE NOW CONFIRMED for trading interval 26-Mar-2025 16:35.
In accordance with Market Notice 125965 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - TAS region - 26/03/2025
Non-credible contingency event - TAS region - 26/03/2025
At 1551 hrs the Palmerston A 220kV Bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
Approximately 40MW of generation was disconnected.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations