[EventId:202502051745_confirmed] Prices for interval 05-Feb-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:45.
In accordance with Market Notice 124199 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051735_confirmed] Prices for interval 05-Feb-2025 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:35.
In accordance with Market Notice 124196 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW
Manager NEM Real Time Operations
[EventId:202502051735_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 February 2025 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 5 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1735 hrs on 5 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502051545_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 February 2025 15:45
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 5 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Refer to market notice: 124174
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1545 hrs on 5 February 2025.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW
Manager NEM Real Time Operations
[EventId:202502051330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 February 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 5 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 5 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502051300_confirmed] Prices for interval 05-Feb-2025 13:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 13:00.
In accordance with Market Notice 124159 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.