Market Notices

123385MARKET INTERVENTION16/01/2025 04:57:24 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123293

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/01/2025.

The direction update is issued at 1700 hrs 16/01/2025.

Manager NEM Real Time Operations
     
123384MARKET INTERVENTION16/01/2025 04:56:07 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123292

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/01/2025.

The direction update is issued at 1700 hrs 16/01/2025.

Manager NEM Real Time Operations
     
123354POWER SYSTEM EVENTS15/01/2025 10:45:07 PM

Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 15/01/2025

At 2019 hrs the Tomago - Taree (963) 132kV line and the Tomago - Brandy Hill (96C) 132kV line tripped.

AEMO did not instruct load shedding.

AEMO has been advised of disconnection of 80 MW of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123336RESERVE NOTICE15/01/2025 05:22:13 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/01/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123323 is cancelled at 1715 hrs 15/01/2025.

Manager NEM Real Time Operations
     
123326PRICES SUBJECT TO REVIEW15/01/2025 04:55:28 PM

[EventId:202501151700_review] Prices for interval 15-Jan-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123324PRICES SUBJECT TO REVIEW15/01/2025 04:50:21 PM

[EventId:202501151655_review] Prices for interval 15-Jan-2025 16:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123323RESERVE NOTICE15/01/2025 04:51:48 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1222 MW

Manager NEM Real Time Operations
     
123322PRICES SUBJECT TO REVIEW15/01/2025 04:45:24 PM

[EventId:202501151650_review] Prices for interval 15-Jan-2025 16:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123321PRICES SUBJECT TO REVIEW15/01/2025 04:42:04 PM

[EventId:202501151645_review] Prices for interval 15-Jan-2025 16:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     