Market Notices

124060INTER-REGIONAL TRANSFER04/02/2025 05:11:43 AM

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Morang - Dederang No.1 330kV line series capacitor - VIC region - 04/02/2025

At 0449 hrs 04/02/2025 there was an unplanned outage of South Morang - Dederang No.1 330kV line series capacitor.

The following constraint set(s) invoked at 0505 hrs 04/02/2025
V-SMSC

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124056MARKET INTERVENTION04/02/2025 04:08:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 05/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
124041NON-CONFORMANCE03/02/2025 10:46:30 AM

NON-CONFORMANCE Region NSW1 Monday, 3 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 3 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124040GENERAL NOTICE03/02/2025 10:53:29 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 03 Feb 2025 to 07 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 3rd Feb
Mt Gambier Ap (39+ Deg C): 3rd Feb
Port Augusta Ap (39+ Deg C): 3rd Feb, 4th Feb, 6th Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 3rd Feb, 4th Feb

VIC
Mildura Ap (39+ Deg C): 4th Feb, 6th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
124020INTER-REGIONAL TRANSFER02/02/2025 10:38:53 PM

Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124017INTER-REGIONAL TRANSFER02/02/2025 10:04:02 PM

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123999MARKET INTERVENTION02/02/2025 09:08:43 AM

Cancellation - AEMO Intervention Event - SA region 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 01/02/2025

Refer to Market Notice 123988

The AEMO Intervention Event and all associated directions are cancelled from 0900 hrs on 02/02/2025.


Manager NEM Real Time Operations
     
123998MARKET INTERVENTION02/02/2025 09:02:34 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123989

Direction is cancelled from: 0900 hrs 02/02/2025

Manager NEM Real Time Operations
     
123989MARKET INTERVENTION01/02/2025 04:07:25 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123988


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 01/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0030 hrs 02/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1130 hrs 02/02/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     