Market Notices

125341SETTLEMENTS RESIDUE06/03/2025 04:00:36 PM

[EventId:202503061600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 March 2025 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 6 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 6 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125338MARKET INTERVENTION06/03/2025 04:00:24 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125275

TORRB2 TORRENS ISLAN at 0730 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/03/2025.

The direction update is issued at 1600 hrs 06/03/2025.

Manager NEM Real Time Operations
     
125336MARKET INTERVENTION06/03/2025 04:00:14 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125274

PPCCGT PELICAN POINT at 0700 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1700 hrs 07/03/2025.

The direction update is issued at 1600 hrs 06/03/2025.

Manager NEM Real Time Operations
     
125293SETTLEMENTS RESIDUE05/03/2025 07:05:24 PM

[EventId:202503051905_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 March 2025 19:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 5 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.

Refer to market notice: 125282

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1905 hrs on 5 March 2025.

This is an AEMO autogenerated Market Notice.
     
125282SETTLEMENTS RESIDUE05/03/2025 06:05:16 PM

[EventId:202503051805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 March 2025 18:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1805 hrs on 5 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 5 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125275MARKET INTERVENTION05/03/2025 04:30:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125259

TORRB2 TORRENS ISLAN at 0400 hrs 06/03/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/03/2025.

The direction update is issued at 1630 hrs 05/03/2025.

Manager NEM Real Time Operations
     
125274MARKET INTERVENTION05/03/2025 04:00:26 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125258

PPCCGT PELICAN POINT at 0400 hrs 06/03/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 07/03/2025.

The direction update is issued at 1600 hrs 05/03/2025.

Manager NEM Real Time Operations
     
125273POWER SYSTEM EVENTS05/03/2025 02:03:49 PM

Update - Non-credible contingency event - NSW region - 05/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 05/03/2025

Refer AEMO Electricity Market Notice 125268

At 1400 hrs the Directlink DC1 was returned to service.

(At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line was returned to service.)

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
125268POWER SYSTEM EVENTS05/03/2025 11:57:45 AM

Non-credible contingency event - NSW region - 05/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 05/03/2025

At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line and the Directlink DC1 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     