125393RECLASSIFY CONTINGENCY08/03/2025 02:37:06 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 08/03/2025 14:37 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
125392RECLASSIFY CONTINGENCY08/03/2025 02:37:05 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 08/03/2025 14:37 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125389PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081305_confirmed] Prices for interval 08-Mar-2025 13:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:05.

In accordance with Market Notice 125376 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125388PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081330_confirmed] Prices for interval 08-Mar-2025 13:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:30.

In accordance with Market Notice 125383 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125387PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081325_confirmed] Prices for interval 08-Mar-2025 13:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:25.

In accordance with Market Notice 125382 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125386PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081320_confirmed] Prices for interval 08-Mar-2025 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:20.

In accordance with Market Notice 125381 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125385PRICES UNCHANGED08/03/2025 01:30:26 PM

[EventId:202503081315_confirmed] Prices for interval 08-Mar-2025 13:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:15.

In accordance with Market Notice 125379 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125384PRICES UNCHANGED08/03/2025 01:30:26 PM

[EventId:202503081310_confirmed] Prices for interval 08-Mar-2025 13:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:10.

In accordance with Market Notice 125378 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125366MARKET SYSTEMS07/03/2025 03:01:51 PM

Inital - CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release

Change Number: CHG0101876

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release
Change Start Date & Time: 12/03/2025 13:00:00
Change End Date & Time: 12/03/2025 17:00:00
Outage Start Date & Time: 12/03/2025 13:00:00
Outage End Date & Time: 12/03/2025 17:00:00

Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm