Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/03/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.125606 is cancelled at 1840 hrs 13/03/2025.
Manager NEM Real Time Operations
[EventId:202503131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 March 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.
Refer to market notice: 125605
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 March 2025.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1668 MW
The minimum capacity reserve available is 1530 MW
Manager NEM Real Time Operations
[EventId:202503131740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 March 2025 17:40
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 13 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1740 hrs on 13 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - TAS region - 12/03/2025
Update - Non-credible contingency event - TAS region - 12/03/2025
Refer AEMO Electricity Market Notice 125564
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Ulverstone - Emu Bay 110kV Line and the Ulverstone - Sheffield tee Paloona 110kV Line
Duration: 1500 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 12/03/2025
Update - Non-credible contingency event - TAS region - 12/03/2025
Refer AEMO Electricity Market Notice 125556
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: TAS
Elements: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Duration: 1400 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 12/03/2025
Non-credible contingency event - TAS region - 12/03/2025
At 1303 hrs the Ulverstone - Emu Bay 110kV Line and the Ulverstone - Sheffield tee Paloona 110kV Line tripped and auto reclosed.
AEMO did not instruct load shedding.
Approximately 12MW of bulk electrical load was disconnected momentarily.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 12/03/2025
Update - Non-credible contingency event - TAS region - 12/03/2025
Refer AEMO Electricity Market Notice 125555
Updated elements: Sheffield George Town No. 1 220kV Line, Sheffield George Town No. 2 220kV Line plus 40 MW load loss at Nystar and 56 MW load loss at Temco.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 12/03/2025
Non-credible contingency event - TAS region - 12/03/2025
At 1200 hrs the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie 2 110kV Line and the Ulverstone - Emu Bay 110kV Line tripped.
AEMO did not instruct load shedding.
AEMO has been advised that 43MW of bulk electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations