Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Refer to Market Notice 128424
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 05/08/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128432
Direction is cancelled from: 1430 hrs 05/08/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128427
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 05/08/2025.
The direction update is issued at 1600 hrs 04/08/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.
AEMO Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128425
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/08/2025.
The direction update is issued at 1435 hrs 03/08/2025.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128424
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 02/08/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 03/08/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 04/08/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations