Market Notices

124575RESERVE NOTICE12/02/2025 07:42:14 PM

Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025

The Actual LOR2 Condition in the SA Region advised in AEMO Electricity Market Notice No.124573 is cancelled at 1940 hrs 12/02/2025.

Manager NEM Real Time Operations
     
124573RESERVE NOTICE12/02/2025 07:15:02 PM

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR2 condition is forecast to exist until 1930 hrs

The capacity reserve required is 245 MW
The minimum reserve available is 107 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
     
124560MINIMUM SYSTEM LOAD12/02/2025 03:04:06 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 124467 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 2012 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


AEMO Operations
     
124467MINIMUM SYSTEM LOAD11/02/2025 02:43:06 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 124437 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1200 hrs to 1500 hrs 16/02/2025. Minimum regional demand is forecast to be 1873 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


AEMO Operations
     
124437MINIMUM SYSTEM LOAD10/02/2025 03:30:40 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


AEMO Operations
     
124301POWER SYSTEM EVENTS07/02/2025 03:34:46 PM

Update - Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 23/01/2025

Refer AEMO Electricity Market Notice 123615

At 0240 hrs on the 23/01/2025 there was a trip and auto reclose of the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
124181POWER SYSTEM EVENTS05/02/2025 03:22:35 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124044

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will cancel the reclassification of this event as a credible contingency event.

Manager NEM Real Time Operations
     
124044POWER SYSTEM EVENTS03/02/2025 02:13:15 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124043

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     