Inter-regional transfer limit variation - Palmerston A 220kV Bus - TAS region - 26/03/2025
Inter-regional transfer limit variation - Palmerston A 220kV Bus - TAS region - 26/03/2025
Refer to Market Notice 125962.
The following constraint set(s) invoked from 1600 hrs to 1620 hrs 26/03/2026.
T-LIPM_WACB
T-LIPM_WACB_SL_N-2
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 125898
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 26/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 27/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1630 hrs 27/03/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125943
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 28/03/2025.
The direction update is issued at 1600 hrs 26/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125906
Direction is cancelled from: 0400 hrs 26/03/2025
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025
Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025
A planned outage of Lower Tumut - Canberra 07 330kV Line in the NSW region was scheduled from 1746 hrs 21/03/2025 to 1800 hrs 26/03/2025.
The outage has been completed and Lower Tumut - Canberra 07 330kV Line returned to service at 1555 hrs 25/03/2025
Constraint set(s) revoked: N-CNLT_07
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125898
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 25/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 26/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 27/03/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125908
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/03/2025.
The direction update is issued at 1600 hrs 25/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125900
Direction is cancelled from: 0400 hrs 25/03/2025
Manager NEM Real Time Operations
[EventId:202503241815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 March 2025 18:15
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 24 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 March 2025.
Refer to market notice: 125915
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 24 March 2025.
This is an AEMO autogenerated Market Notice.